443 Infra Projects Hit by Cost Overrun of Rs 4.92 Lakh Crore in February – News 18 


If the delay is calculated based on the latest schedule of completion, the number of delayed projects reduces to 568.

If the hold-up is computed based upon the most recent routine of conclusion, the variety of postponed tasks minimizes to 568.

Of the 1,902 tasks, 443 have actually reported price overruns and 764 tasks have actually been postponed.

The price of 443 facilities tasks, each entailing a financial investment of Rs 150 crore or even more, had actually intensified to greater than Rs 4.92 lakh crore in February 2024, a main record stated. According to the Ministry of Statistics and Program Implementation (MoSPI), which keeps track of facilities tasks worth Rs 150 crore and over, out of 1,902 tasks, 443 had actually set you back overruns and 764 tasks were postponed.

“The complete initial price of execution of 1,902 tasks was Rs 27,08,030.44 crore, and their approximated complete price is most likely to be Rs 32,00,507.55 crore, standing for a total price overrun of Rs 4,92,477.11 crore (18.19 percent of the initial price).Is ), “stated the ministry’s most current record for February 2024.

According to the record, till February 2024, the expense on these tasks was Rs 16,76,739 crore, which is 52.39 percent of the approximated price of the tasks.

However, if the hold-up is computed based upon the most recent routine of conclusion, the variety of postponed tasks minimizes to 568.

Additionally, it stated that for 389 tasks, neither the year of appointing neither the possible building duration has actually been reported.

Of the 764 postponed tasks, 188 have an overall hold-up of 1-12 months, 185 have a hold-up of 13-24 months, 275 tasks have a hold-up of 25-60 months, and 116 tasks have a hold-up of greater than 60 months.

The ordinary time overrun in these 764 postponed tasks is 36.27 months.

As explained by different job applying firms, factors for time overruns consist of hold-ups in land procurement, acquiring woodland and atmosphere clearances, and absence of facilities assistance and links.

Delays in tie-up for job funding, completion of thorough design, adjustments in extent, tendering, buying and tools supply, and order issues are amongst the various other factors.

The record additionally pointed out state-wise lockdowns as a result of COVID-19 (enforced in 2020 and 2021) as the factor for the hold-up in execution of these tasks.

It has actually additionally been observed that job applying firms are not reporting modified price price quotes and appointing routines for numerous tasks, which recommends that time/cost overrun numbers are under-reported.

(This tale has actually not been modified by News 18 team and is released from a syndicated news company feed – PTI,



Source link

Vardan Patterson
Vardan Pattersonhttps://topworldnewz.com
My name is Vardan Patterson I live in Ghaziabad, India I am a B.SC graduate in Network Technology, UEM Engineer and as a hobby I created this website. I also have a youtube channel where you can watch facts videos. If you want to connect with me you can use our website’s contact us page or you can connect with me on my Instagram by clicking here or you can send me an email at vardan.patterson@topworldnewz.com. Thank you for your visit on my website

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Must Read